Temporary works · bridges · buildings

Falsework Design Studio

Lay out a falsework system, follow the load from the fresh concrete down to the ground, and check every member: sheathing, joists, stringers, caps and posts. The beam engine solves continuous and simple spans, the drawings are to scale with dimensions, and the calc report prints on 8.5×11 paper.

Phase 1 covers full-support falsework for slab bridges, box girders, T-beams, building slabs and any custom section. Results update as you type, and your work saves automatically in this browser.

01 · Studio

Project

02 · Studio

Design basis

Pick the criteria set that governs the work. Every value stays editable, so you can match contract special provisions.

Criteria set

Vertical loads

Member design methods

Horizontal loads & special locations

03 · Studio

Structure & loads

Describe the concrete the falsework carries. The studio splits the section into zones of equal thickness across the falsework width and turns each zone into a design pressure.

04 · Studio

Falsework layout

Joists run across the bridge on longitudinal stringers. Stringers span between bents, and each bent has a cap on a row of posts.

Joists & stringers

Bents & posts

Deflection allowances

05 · Studio

Members

Choose material, size, grade and span condition for each level of the falsework. Auto-size members picks the lightest listed section that passes, top to bottom.

06 · Studio

Results summary

Notes & warnings

    07 · Studio

    Drawings

    Every drawing uses one declared scale for both directions, with dimension strings and a graphic scale bar. At 100% print size the stated scale is true.

    08 · Studio

    Member calculations

    Each member shows its loads, section properties, allowable values, analysis diagrams and checks. The governing case is highlighted.

    09 · Studio

    Horizontal loads

    The bracing must resist the larger of the percentage of dead load, any minimum, and wind, applied at the top of the posts in any direction. Bracing member design comes in Phase 2.

    10 · Studio

    Deflection & camber

    Falsework deflection under the concrete weight is added to the screed grades so the finished soffit lands on profile. Add the bridge plan camber separately.

    11 · Studio

    Calculation report

    Letter-size pages with header, footer and page numbers. The report rebuilds a moment after each change.

    12 · Studio

    Project records

    Each project has a unique ID. Records are kept in this browser; export a project file to move it to another computer.

    C1 · Course

    Falsework, formwork and shoring

    Falsework is the temporary structure that holds a permanent structure in place until it can carry itself. On a cast-in-place bridge it carries the fresh concrete, the reinforcing steel, the forms, the crew and their equipment. The Caltrans definition covers the steel or timber beams, girders, posts, foundations and any other members that support the permanent work during construction.

    Formwork is the mold that gives concrete its shape: plywood soffits, side forms, bulkheads and the studs and walers that stiffen them. Falsework holds the formwork up. Shoring is the general word for vertical supports, most often used for building slabs. Reshoring is shoring placed after the original forms are stripped, so the load of new floors above is shared with the floors below.

    Typical timber bent under a cast-in-place slab bridge, drawn to scale from the INDOT slab example.
    Key idea. Falsework fails in a few predictable ways: a member is overstressed, a bearing crushes, the system sways because bracing is missing, or the ground settles. Every check in this studio targets one of those.
    C2 · Course

    Roles, submittals and drawings

    The contractor is responsible for the design, construction and safety of falsework. A licensed engineer prepares the drawings and calculations when the contract requires it. The owner's engineer reviews them for compliance with the contract criteria. Review does not move design responsibility to the owner. Changes in the field need revised drawings from the falsework engineer before concrete is placed.

    Check the governing contract first. For IDOT work, start with Standard Specifications Section 503 (Concrete Structures) and the special provisions. Caltrans work follows Standard Specifications Section 48-2 and the Falsework Manual. Cal/OSHA Title 8 §1717 sets its own requirements for falsework and vertical shoring.

    Falsework drawings should show

    Field tip. Walk the falsework with the drawings before the pour. Check member sizes, post plumbness, wedges in matched pairs, bracing connections and pad bearing. Most problems are visible before the concrete truck arrives.
    C3 · Course

    Design criteria compared

    The three criteria sets built into the studio agree on the big numbers but differ in detail. Always confirm against the edition named in your contract.

    ItemCaltrans Falsework Manual / Std Spec 48-2INDOT memo / AASHTO-styleACI 347 (buildings)
    Concrete160 pcf normal, 130 pcf lightweight (includes forms and rebar)150 pcf concrete and rebar150 pcf normal-weight concrete and rebar
    FormsIncluded in 160 pcf+15 psfActual form weight
    Live load20 psf over the total area supported, plus actual equipment as concentrated loads20 psf plus known construction loads50 psf minimum, 75 psf with motorized carts
    Edge load75 plf at the outside edge of deck overhangs; 20-ft loaded zone for members below the soffit when spans exceed 20 ft75 plf at overhangsNot specified
    Minimum total100 psf on any member100 psf100 psf, 125 psf with motorized carts
    HorizontalActual loads plus wind, but not less than 2% of total dead load, at the top of the posts, loaded and unloadedPer contractGreater of 100 plf of edge or 2% of total dead load
    WindHeight-zone coefficients × Q, Q = 1 + 0.2W ≤ 10Per contractPer project; enclosures add load
    DeflectionL/240 under concrete weight (150 pcf)Per contractPer surface class
    TimberNDS, CD = 1.25 (1.6 wind)NDSNDS
    SteelAISC with Caltrans flexural compression 12,000,000/(Ld/bt)AISCAISC
    TrafficPosts and towers over or next to traffic designed for 150% of the calculated loadPer contract—
    C4 · Course

    Vertical loads

    The vertical design load is dead load plus live load, but never less than the minimum total load. Dead load is the concrete, reinforcing steel, forms and the self-weight of each falsework member. Live load covers workers, tools and equipment. The minimum covers small loads nobody wrote down: material staging, a pile of rebar, a buggy.

    Because concrete thickness changes across a section, the design pressure changes too. Under a box girder web the falsework sees the full girder depth; under a cell it sees only the top and bottom slabs.

    Box girder section with design pressure by zone, Caltrans criteria.
    Exam and review tip. When a thin slab is checked, the minimum total load usually governs. A 5-inch slab weighs only 67 psf at 160 pcf, so 67 + 20 = 87 psf is raised to 100 psf.
    C5 · Course

    Horizontal loads and wind

    Falsework must be braced for a horizontal load in any direction. Caltrans uses the sum of actual horizontal loads plus wind, but not less than 2% of the total dead load at the location, applied at the top of the posts. The check is made with the falsework both loaded and unloaded. ACI 347 uses the greater of 100 plf along the slab edge or 2% of the dead load.

    For timber posts and other conventional falsework, Caltrans wind pressure is a velocity coefficient for each height zone times a drag factor Q = 1 + 0.2W (not more than 10), where W is the width of the falsework in the wind direction. Wind on each height zone gives an overturning moment, and dividing by the height to the top of the posts gives the design wind load at that level.

    Wind on a bent: height zones, impact areas and the equivalent load at the top of the posts.
    Rule of thumb. The 2% load usually governs below about 30 ft. Wind starts to govern above 30 to 40 ft and on wide, tall falsework.
    C6 · Course

    Falsework systems

    Timber post and beam bents

    The common highway system: timber posts on sills and pads, a timber or steel cap, timber or steel stringers and timber joists. Grade is set with hardwood wedges at the top or bottom of the posts. It is cheap and flexible but labor-heavy, and posts are limited by slenderness.

    Pipe post bents with steel caps

    Steel pipe columns carry heavier loads over taller heights. A braced pipe bent behaves as a rigid frame with top and bottom caps. Grade adjustment is made at the top or bottom with wedges or jacks.

    Pipe post bent with steel cap and steel stringers, drawn to scale.

    Heavy-duty steel shoring towers

    Proprietary towers carry up to about 100 kips per leg and permit long falsework spans. Capacity comes from the manufacturer's tested values for the actual extension, bracing and load eccentricity. Phase 2 adds tower design.

    Heavy-duty shoring tower with screw jacks, frames and cap beams, to scale.

    Spans over traffic

    Steel beams span openings over live traffic on bents protected by temporary barrier. Caltrans increases post and tower loads to 150% next to traffic and requires positive connections that resist impact. Phase 3 adds openings, clearances and crash-protection checks.

    Falsework opening over a two-lane roadway, to scale.

    Building shoring and reshoring

    Floors are formed on joists and stringers carried by adjustable steel or aluminum shores. After stripping, reshores share the weight of the next floor with the floors below. The number of levels of reshores depends on cycle time and slab strength.

    Shoring and two levels of reshores in a flat-plate building, to scale.
    C7 · Course

    The load path

    Load moves down through a stack of members, and each interface is a bearing check. The studio follows the same order: sheathing, joists, stringers, caps, posts, then sills and pads.

    Exploded load path of a typical timber and steel falsework, to scale.
    MemberSpans betweenMain checks
    SheathingJoistsBending, rolling shear, deflection (APA method)
    JoistsStringersBending, shear, deflection, bearing on stringer
    StringersBentsBending (lateral stability), shear, deflection, bearing on cap, web yielding
    CapsPostsBending, shear, deflection, bearing over posts
    PostsCap to sillAxial compression with buckling, slenderness, bearing
    Sills & padsSoilBearing pressure, bending of the sill (Phase 2)
    C8 · Course

    Sheathing design

    Plywood soffit forms are designed per foot of width using the APA Plyform properties: effective section modulus KS, moment of inertia I and rolling shear constant Ib/Q. Panels usually run across three or more joists, so the continuous three-span coefficients apply. Bending uses the center-to-center span, shear uses the clear span, and deflection uses the clear span plus a small allowance (1/4 in. for 2-in. lumber, 5/8 in. for 4-in. lumber).

    Practical note. Under box girder webs the pressure can pass 1,000 psf. Designers reduce joist spacing to 8–12 in. or use thicker panels there. The Auto-size button tries thicker panels first, then closer joist spacing.
    C9 · Course

    Timber beams (NDS)

    Current Caltrans practice designs timber with the NDS. Each reference design value is multiplied by adjustment factors: load duration CD = 1.25 for falsework loads (1.6 for wind), wet service CM when moisture content exceeds 19%, size factor CF, beam stability CL, and repetitive member Cr for closely spaced dimension lumber.

    FactorApplies toTypical value in falsework
    CD load durationFb, Fv, Fc (not Fc⊥ or E)1.25 construction loads, 1.6 wind
    CM wet serviceAll1.0 dry; dimension lumber wet: Fb 0.85, Fv 0.97, Fc⊥ 0.67, Fc 0.8, E 0.9
    CF sizeFb, FcTable values for 2"–4" lumber; (12/d)^(1/9) for timbers deeper than 12"
    CL beam stabilityFb1.0 when the compression edge is braced or d/b ≤ 2
    Cr repetitiveFb of 2"–4" lumber1.15 when three or more members at 24" or less share load
    Cb bearing areaFc⊥(ℓb + 0.375)/ℓb for bearing lengths under 6"
    C10 · Course

    Steel beams

    Steel stringers and caps are usually rolled W-shapes. Caltrans limits flexural compression stress to 12,000,000/(Ld/bt) psi, where L is the unbraced length of the compression flange, d the depth, b the flange width and t the flange thickness. The limit is 22,000 psi for unidentified or A36 steel and 0.6Fy for other identified grades. The AISC 360 option uses the lateral-torsional buckling rules of Chapter F with Ω = 1.67.

    Don't forget. Where a steel beam sits on a cap or a post, check web yielding, web crippling and flange bending. Caltrans research on cap and sill flange failures led to added design equations for these limit states.
    C11 · Course

    Bearing perpendicular to grain

    Wherever one member sits on a timber member, the contact area is checked against Fc⊥. The load duration factor does not apply to Fc⊥. When the bearing length is under 6 in. and at least 3 in. from the end of the member, the bearing area factor Cb raises the allowable value.

    Field tip. Crushing at caps and sills shows up as wedges biting in and grades dropping after the pour starts. Use steel plates or hardwood corbels when the contact area is small.
    C12 · Course

    Posts and columns

    Posts are checked as columns. For timber, the NDS column stability factor Cp depends on the slenderness Le/d, which may not exceed 50. Steel pipe posts use AISC 360 Chapter E, or the Caltrans formula 16,000 − 0.38(L/r)² psi for unidentified steel with L/r ≤ 120. Manufactured shores and tower legs use the manufacturer's allowable load for the actual extension and bracing.

    C13 · Course

    Deflection, camber and settlement

    Before the pour, the soffit is set high so it settles onto the design profile. The adjustment adds the elastic deflection of the stringers, caps and joists under concrete weight, the shortening of the posts, joint take-up at each wood contact, and expected settlement of the pads. The bridge plan camber for permanent dead load is added on top.

    Components of falsework settlement along a span (vertical scale exaggerated).
    C14 · Course

    Box girders and T-beams

    A cast-in-place box girder is usually placed in two pours: the bottom slab and stems first, then the deck. Falsework is still designed for the full section, because the first pour is not yet structural when the deck goes on. Caltrans allows the stems to be treated as self-supporting between bents only when the bent spacing does not exceed four times the first-pour stem depth and the deck is placed more than 5 days after the stems.

    For T-beams, the stems concentrate load the same way box webs do. Place stringers under the stems where you can, and check the stringer under each stem with its full tributary load.

    C15 · Course

    Vertical form pressure (preview)

    Walls, columns and pier cap sides are loaded by the lateral pressure of fresh concrete. ACI 347 gives the maximum pressure from the rate of placement R (ft/hr), concrete temperature T (°F), a unit weight coefficient Cw and a chemistry coefficient Cc. Phase 3 adds full form and tie design.

    C16 · Course

    Inspection checklists

    Tick items as you inspect. Ticks save with the project.

    C17 · Course

    Failure modes and lessons learned

    Lesson. Most collapses happen in the field, not on paper. Inspection before and during the pour, and discipline about changes, matter as much as the calculations.
    C18 · Course

    Glossary

    C19 · Course

    Roadmap: Phases 2–4

    Phase 2

    • Deck overhang brackets and exterior girder rotation
    • Heavy-duty shoring towers
    • Diagonal bracing, overturning and longitudinal stability
    • Sills, pads, corbels and soil bearing

    Phase 3

    • Wall, column and pier cap form pressure, ties and walers
    • Building shoring and reshoring by floor cycle
    • Traffic openings, clearances, impact connections
    • Pier cap falsework on collars

    Phase 4

    • Reviewer mode for contractor falsework submittals
    • Comment log export
    • Pre-pour, pour and removal inspection reports
    C20 · Course

    References

    Limitations. This studio is a design-and-check aid. Library section properties and reference design values are typical published values and should be verified against the editions in your contract. Final falsework drawings and calculations remain the responsibility of the falsework engineer.

    FALSEWORK DESIGN STUDIO · ENG. AHMAD SAFI, PE